1.2.3
In case of Joint Venture
Partnership / Collaboration, it should be valid for the entire
duration of the Contract. Documentary evidence of having collaboration
must specify clearly the role and responsibility of each partner/collaborator
to provide the manpower/ equipment/ technology or services for
completion of the work as per provisions of the Contract. An undertaking
by all the parties to this effect must be submitted along with
the bid.
1.2.4
The primary bidder must
confirm to furnish an undertaking to the Company (OIL) for a single-point
responsibility for execution / completion of the project in all
respects under the Terms of Reference (TOR)/Technical Specifications
of this tender.
1.2.5
The Bidder must confirm
to provide the key personnel of requisite experience and qualification
as specified in Terms of Reference (Personnel list enclosed in
Annexure-I).
1.2.6
The bidder must confirm
their compliance of the following in their 'Techno-Commercial'
Bid: -
- Status of possession of compressor; whether owned by outright
purchase or hired on lease or to be purchased brand new must
be submitted at the time of bidding. In case of hiring, Memorandum
Of understanding covering the entire contract period must
be submitted to the company.
- The compressor to be offered must have the following specifications:
-
- Date of manufacture of the compressor and the vehicle
should not be of earlier than 01.01.2000
- Capacity of the compressor: to operate and supply of
compressed air at a minimum discharged rate of 6.0 Cubic
metre per minute up to an operating pressure of 120 Kg/cm²
at exit temperature not exceeding 70°C.
-
- The compressor to be offered must have of make of
any one of the following reputed companies: Khosla /
Ingersoll Rand / Burckhardt Compression / Atlas Capco
/ Elgi /Kirloskar.
-
- The dimension of the entire unit along with the vehicle
should not be more the followings:
Length: 10.0 metre
Breadth: 3.0 metre
Height: 4.0 metre from the ground level
Note: In support of 1.2.6 above,
documentary evidence from the original equipment manufacturer
must be submitted along with the bid.
In case of offering brand new compressor unit, the bidder
must confirm the compliance of providing the unit as per
the specification as mentioned above.
- To complete the mobilisation within 60 (sixty) days from
the date of issue of the Letter of Award (LOA).(documentary
evidence from original manufacturer regarding the capability
to supply the equipment within the stipulated time frame is
to be furnished in case of new purchase ) For delay the Contractor
will be levied liquidated damages at the rate of 0.5% per
week or part thereof of the total fixed charge as per clause16.0
of Part -VI subject to a maximum of 10%.
2.0 COMMERCIAL
2.1
The bids are to be submitted
in a single stage under 2(two) bid system i.e. Technical bid (un-priced)
and Commercial bid (priced) together as per Section-II Clause
5.0 of the Tender.
2.2
The Bidder shall furnish
Bid Security along with Bid as referred to in Para 10 of Section
II. Bid security shall be furnished as a part of technical bid.
The amount of bid security should be as specified in the 'Forwarding
letter'. Any bid not accompanied by a proper bid security will
be rejected.
2.3 Any
bid received through Telex/Cable/Fax/Email will not be accepted.
2.4
Bid shall be typed or
written in indelible ink and original bid shall be signed by the
Bidder or their authorized representative on all pages.
2.5
Bid shall contain no
interlineations, erasures or overwriting except as necessary to
correct errors made by Bidder, in which case such corrections
shall be initialed by the person(s) signing the bid. However,
white fluid should not be used for making corrections. Any bid
not meeting this requirement shall be liable for rejected.
2.6 Any
bid containing false statement will be liable for rejection
2.7
Bidders must quote clearly
and strictly in accordance with the price schedule outlined in
Price Bid Format given in SECTION-V, of bidding documents; otherwise
the bid will be liable for rejection
2.8
There should not be
any indication of price, CIF value etc. in the technical bid.
A bid will be straightway rejected if these are given in the technical
bid.
2.9
The bid documents are
not transferable. Offers received from unsolicited bidders will
be ignored.
2.10
Offers quoted by Indian
agents on behalf of their foreign principals will not be accepted
and the same will be summarily rejected.
2.11
Any Bid received by
the Company after the deadline for submission of bids prescribed
by the Company will be rejected.
2.12
Price quoted by the
successful Bidder must be fixed during its performance of the
contract and not subject to variation on any account. A bid submitted
with an adjustable price quotation will be treated as non-responsive
and rejected.
2.13
The following Clauses
with all its sub-clauses should be agreed in toto, failing which
the bid will be rejected.
- Performance Security Clause
- Taxes Clause
- Insurance Clause
- Force Majeure Clause
- Termination Clause
- Arbitration Clause
- Liability Clause
- Withholding Clause
- Applicable Law Clause
- Obligation of Contractor Clause
3.0 GENERAL:
3.1
In case bidder takes
exception to any clause of Bidding Document not covered under
BEC/BRC, then the Company has the discretion to load or reject
the offer on account of such exception if the bidder does not
withdraw/ modify the deviation when/as advised by the Company.
The loading so done by the Company will be final and binding on
the Bidders. No deviation will however, be accepted in the clauses
covered under BRC.
3.2
To ascertain the substantial
responsiveness of the bid the Company reserves the right to ask
the Bidder for clarification in respect of clauses covered under
BRC also and such clarification fulfilling the BRC clauses must
be received on or before ten days from the date of clarification
sought by the Company, failing which the bid will be summarily
rejected.
3.3
In case, any of the
clauses in the BRC contradict with other clauses of Bidding Document
elsewhere, then the clauses in the BRC shall prevail.
3.4
Any exceptions/deviations
to the tender must be spelt out by bidder in their 'Techno-Commercial'
bid only. Any additional information/terms/ conditions furnished
in the 'Price Bid' will not be considered by OIL for evaluation/award
of Contract.
( B. K. BORAH )
CHIEF MANAGER (CONTRACTS)